Removal and Replacement of Telemetry Cabinets for Existing SCADA System - Phased Projects
Summary
The proposed work will be contracted to a licensed Florida General or Electrical Contractor for the removal and replacement of Telemetry Cabinets for the existing Supervisory, Control, And Data Acquisition (SCADA) System in a series of phased projects. Also, said Contractor shall provide all labor, materials, equipment, and incidentals required to construct as detailed in the contract documents. The overall work includes, but is not limited to the following: Replacement of thirty-three (33) telemetry cabinets as further specified in the Bid document. As previously stated, this will be a phased project. This contract will be an initial three (3) year period with the option to renew for an additional one (1) year, in the AUTHORITY’s sole and unfettered discretion. Small Business Enterprise (SBE) Participation: No API Each bid submittal shall include a Bid Security in the form of a surety company Bid Bond or Cashier's check (check submitted in advance) in an amount of not less than five percent (5%) of the total bid amount. Questions and Answers: The AUTHORITY provides a specified time for BIDDERS to ask questions and seek clarification regarding the requirements of the solicitation. All questions or clarification inquiries must be submitted through Bonfire by the date and time specified in the bid document (including any addenda). The AUTHORITY will respond to all questions through Bonfire, that may include a written Addendum. Submittal Instructions: BIDDER MUST submit its solicitation response electronically and MUST confirm its submittal in order for the Authority to receive a valid response through Bonfire. Refer to Bonfire for submittal instructions. It is the BIDDER's sole responsibility to assure its response is submitted and received through Bonfire by the date and time specified in the solicitation. The AUTHORITY will not consider bid responses received by other means. BIDDERS are encouraged to submit their responses in advance of the due date and time specified in the solicitation document. In the event that the BIDDER is having difficulty submitting the solicitation document through Bonfire, immediately notify the Bid Contact (Purchasing Agent), and then contact Bonfire for technical assistance.
Details
| Solicitation Number | ITB No.: 27-402/DL |
| Type | ITB |
| Posted | 2026-11-06 1:00PM EST (2 days ago) |
| Response Deadline | 2026-12-16 2:00PM EST (in 1 month) |
| State | FL |
Description
The proposed work will be contracted to a licensed Florida General or Electrical Contractor for the removal and replacement of Telemetry Cabinets for the existing Supervisory, Control, And Data Acquisition (SCADA) System in a series of phased projects. Also, said Contractor shall provide all labor, materials, equipment, and incidentals required to construct as detailed in the contract documents. The overall work includes, but is not limited to the following: Replacement of thirty-three (33) telemetry cabinets as further specified in the Bid document. As previously stated, this will be a phased project. This contract will be an initial three (3) year period with the option to renew for an additional one (1) year, in the AUTHORITY’s sole and unfettered discretion. Small Business Enterprise (SBE) Participation: No API Each bid submittal shall include a Bid Security in the form of a surety company Bid Bond or Cashier's check (check submitted in advance) in an amount of not less than five percent (5%) of the total bid amount. Questions and Answers: The AUTHORITY provides a specified time for BIDDERS to ask questions and seek clarification regarding the requirements of the solicitation. All questions or clarification inquiries must be submitted through Bonfire by the date and time specified in the bid document (including any addenda). The AUTHORITY will respond to all questions through Bonfire, that may include a written Addendum. Submittal Instructions: BIDDER MUST submit its solicitation response electronically and MUST confirm its submittal in order for the Authority to receive a valid response through Bonfire. Refer to Bonfire for submittal instructions. It is the BIDDER's sole responsibility to assure its response is submitted and received through Bonfire by the date and time specified in the solicitation. The AUTHORITY will not consider bid responses received by other means. BIDDERS are encouraged to submit their responses in advance of the due date and time specified in the solicitation document. In the event that the BIDDER is having difficulty submitting the solicitation document through Bonfire, immediately notify the Bid Contact (Purchasing Agent), and then contact Bonfire for technical assistance.
Contact
| Email / phone | 🔒 Available with Pro Upgrade |
Documents
-
📄 ITB 27-402 - Removal & Replacement of Telemetry Cabinets.pdf DocumentationComplete Invitation to Bid document.
-
📄 ITB 27-402 - Section 00300 - Project Experience Forms 1-3.pdf DocumentationProject Experience Forms
-
📄 Section 01005 - General Requirements - 09292026.pdf DocumentationSpecifications - General Requirements
-
📄 Section 01041 - Project Coordination - 09292026.pdf DocumentationSpecifications - Project Coordination
-
📄 Section 01014 - Construction Sequence - 08182026.pdf DocumentationSpecifications - Construction Sequence
-
📄 Section 01100 - Special Project Procedures - 09292026.pdf DocumentationSpecifications - Special Project Procedures
-
📄 Section 01025 - Measurement and Payment - 09082026.pdf DocumentationSpecifications - Measurement and Payment
-
📄 Section 01102 - Safety Health and Emergency Response Requirements - 08182026.pdf DocumentationSpecifications - Safety Health and Emergency Response Requirements
-
📄 Section 01310 - Progress Schedules - 08182026.pdf DocumentationSpecifications - Progress Schedules
-
📄 Section 01153 - Change Order Procedures - 08182026.pdf DocumentationSpecifications - Change Order Procedures
-
📄 Section 01152 - Applications for Payment - 08182026.pdf DocumentationSpecifications - Applications for Payment
-
📄 Section 01370 - Schedule of Values - 08182026.pdf DocumentationSpecifications - Schedule of Values
-
📄 Section 01610 - Material and Equipment - 08182026.pdf DocumentationSpecifications - Material and Equipment
-
📄 Section 160501 - Basic Electrical Materials and Methods - 08182026.pdf DocumentationSpecifications - Basic Electrical Materials and Methods
-
📄 Section 01740 - Warranties and Bonds - 08182026.pdf DocumentationSpecifications - Warranties and Bonds
-
📄 Section 160533 - Raceways and Boxes for Electrical Systems - 08182026.pdf DocumentationSpecifications - Raceways and Boxes for Electrical Systems
-
📄 Section 162914 - Telemetry Cabinets - 090826docx.pdf DocumentationSpecifications - Telemetry Cabinets
-
📄 Section 160502 - Miscellaneous Equipment - 08182026.pdf DocumentationSpecifications - Miscellaneous Equipment
-
📄 Section 160519 - Low Voltage Electrical Power Conductors and Cables.pdf DocumentationSpecifications - Low Voltage Electrical Power Conductors and Cables
-
📄 Section 160526 - Grounding and Bonding for Electrical Systems - 08182026.pdf DocumentationSpecifications - Grounding and Bonding for Electrical Systems
-
📄 ITB 27-402 - Section 00300 - Authority to Execute Contract.pdf DocumentationBidder will be required to submit documentation to satisfy this requirement