West County Wastewater District (WCW) is soliciting bids from qualified contractors to provide construction services for the Secondary Sedimentation Basins 1 and 2 Short-Term Improvements Project at the Water Quality & Resource Recovery Plant (WQRRP). WCW identified the need to rehabilitate and upgrade all four secondary sedimentation basins at the WQRRP to maintain reliable operation and treatment performance and retained Black & Veatch to provide engineering design services for the improvements.

The work under this contract is limited to Secondary Sedimentation Basins (SSB) 1 and 2 and generally includes demolition, concrete repairs, coatings, mechanical improvements, site restoration, and all other work necessary to complete the improvements in accordance with the Contract Documents. West County Wastewater District will directly procure and furnish the replacement collector chains and flights for SSB-01 and SSB-02; however, the Contractor shall be fully responsible for receiving, handling, storing, protecting, coordinating, and installing the owner-furnished equipment as part of the Work.

Contractors shall provide all labor, materials, equipment, supervision, and incidentals necessary to complete the project and place the rehabilitated facilities into successful operation in accordance with the Plans and Specifications.

Details

Solicitation Number26-IFB-040
TypeActive
Posted2026-10-27 3:00AM EDT (14 days ago)
Response Deadline2026-12-16 6:00PM EST (in 1 month)
CityRichmond
StateCA
ZIP94806

Description

West County Wastewater District (WCW) is soliciting bids from qualified contractors to provide construction services for the Secondary Sedimentation Basins 1 and 2 Short-Term Improvements Project at the Water Quality & Resource Recovery Plant (WQRRP). WCW identified the need to rehabilitate and upgrade all four secondary sedimentation basins at the WQRRP to maintain reliable operation and treatment performance and retained Black & Veatch to provide engineering design services for the improvements.

The work under this contract is limited to Secondary Sedimentation Basins (SSB) 1 and 2 and generally includes demolition, concrete repairs, coatings, mechanical improvements, site restoration, and all other work necessary to complete the improvements in accordance with the Contract Documents. West County Wastewater District will directly procure and furnish the replacement collector chains and flights for SSB-01 and SSB-02; however, the Contractor shall be fully responsible for receiving, handling, storing, protecting, coordinating, and installing the owner-furnished equipment as part of the Work.

Contractors shall provide all labor, materials, equipment, supervision, and incidentals necessary to complete the project and place the rehabilitated facilities into successful operation in accordance with the Plans and Specifications.