The project is located at the Jay Lively Activity Center in Flagstaff, AZ. The scope of work includes selective demolition of existing water-cooled chillers, evaporative coolers, pumps, air control devices, and piping, and the installation of two new air-cooled chillers, primary chilled water pumps, air control devices, and a hydronic reheat loop. New equipment shall be connected to existing chilled water piping. The new reheat loop shall be connected to the existing heat exchanger HX-2. New controls devices, wiring, and programming shall be provided to integrate all new equipment into the existing BAS system. New chillers shall have BACnet communication. 


Note, new chilled water supply and return mains to the new chillers and pumps are designed at 6”, based on the design flow rate of the new chilled water pumps. The existing chilled water mains (installed under the separate piping project) are designed at 8” to accommodate the existing chilled water pump’s higher flow rate. The new 6” pipe will be connected to the existing 8” mains with reducers. 


A new 1000 amp main electrical switchboard will be provided and installed by the owner to feed the building. An electrical service upgrade will be required to support the new equipment. The City of Flagstaff will coordinate all requirements with the local utility to implement the service upgrade. 

Details

Solicitation Number2027-508
TypeActive
Posted2026-10-15 3:00AM EDT (25 days ago)
Response Deadline2026-11-12 2:00PM EST (in 2 days)
CityFlagstaff
StateAZ
ZIP86001-5359

Description

The project is located at the Jay Lively Activity Center in Flagstaff, AZ. The scope of work includes selective demolition of existing water-cooled chillers, evaporative coolers, pumps, air control devices, and piping, and the installation of two new air-cooled chillers, primary chilled water pumps, air control devices, and a hydronic reheat loop. New equipment shall be connected to existing chilled water piping. The new reheat loop shall be connected to the existing heat exchanger HX-2. New controls devices, wiring, and programming shall be provided to integrate all new equipment into the existing BAS system. New chillers shall have BACnet communication. 


Note, new chilled water supply and return mains to the new chillers and pumps are designed at 6”, based on the design flow rate of the new chilled water pumps. The existing chilled water mains (installed under the separate piping project) are designed at 8” to accommodate the existing chilled water pump’s higher flow rate. The new 6” pipe will be connected to the existing 8” mains with reducers. 


A new 1000 amp main electrical switchboard will be provided and installed by the owner to feed the building. An electrical service upgrade will be required to support the new equipment. The City of Flagstaff will coordinate all requirements with the local utility to implement the service upgrade. 

Contact

NameEmily Markel
Email / phone 🔒 Available with Pro Upgrade